Last month’s tornadoes may end up costing EPB up to $35 million to repair broken poles, lines and equipment for both its power and broadband services – the most expensive storm in the utility’s history.
But the Chattanooga utility hopes to recover most of the damage expenses from the Federal Emergency Management Agency after the federal disaster declaration, which can cover up to 75% of such expenses.
Greg Eaves, chief financial officer for EPB, told the utility’s board Friday that the repair costs continue to mount from the series of seven tornadoes that ripped through EPB’s 600-square-mile area on Easter Sunday night and knocked out power to over 60,000 EPB customers.
EPB initially estimated last month that the storms would cost about $28 million in extra repair costs, but Eaves said the ongoing work is likely to have a final price tag of over $30 million “and maybe as high as $35 million.” EPB is eligible to have up to 75% of such public expenses paid by FEMA following the disaster declaration last month.
“We’ve restored power to everyone and we’re finishing up the fiber restoration,” EPB President David Wade said. “We’ve had to continue throughout the month to finish the rebuilt process for some of the cables, intelliruptors and other equipment that we didn’t initially have to replace or rebuild to get power and fiber back up and running.”