Officials are seeking about $350,000 in city funds to hire a marine engineer to determine how best to fix crumbling concrete and other problems along the docking area at Ross’s Landing.
“It’s not the issue of safety. It’s the issue of things falling apart,” Steve Leach, the city’s public works administrator, told officials of the Chattanooga Downtown Redevelopment Corp. on Wednesday.
Lee Norris, deputy public works administrator, said the concrete boat dock area next to the popular Passage water attraction is stable.
But the Tennessee River’s current is causing a washing out of dirt beneath the water’s surface, he said, which is prompting concrete to crack and fall away as well as uneven settling and a failure of the retaining wall system.
The city already has spent $50,000 to look at the problems on the docking area above and below the surface.