BY THE BIG NUMBERS• 600,000 cubic yards of excavation• 275,000 tons of large graded rock• 57,000 cubic yards of concrete• 80,000 tons of hot mix asphalt• 6 new bridges• 14,000 linear feet of retaining walls, the longest of which is more than 1,000 feet• 12 miles of steel for the retaining walls• 8 miles of steel for the bridges• Almost 2 miles of concrete drainage pipe• 6 large overhead signs spanning the roadway• 44 roadway lights, 20 are 100 feet tallSource: Tennessee Department of Transportation
When roadwork to widen U.S. Highway 27 between the Olgiati Bridge and the Signal Mountain exit is done, the new stretch could be dubbed the “hundred-million-dollar” mile.
The 1.6-mile passage through narrow breaks in the folds of Stringer’s Ridge is budgeted to cost $102.5 million and probably will go over that budget, according to Ken Flynn, the regional construction manager for the Tennessee Department of Transportation.
Because the now four-lane road is in a valley between unstable hills lined with condos, widening it to six lanes and adding adequate acceleration and deceleration space for three sets of on- and off-ramps means moving up the ridge on both sides.
“It’s a big challenge,” said Flynn. “There’s a lot going on in not a lot of space. And there are complications.”