Pisgah High School gym project back on track after tornado damage

94-b4-pisgah-gym-project-back-on-track
94-b4-pisgah-gym-project-back-on-track 94-b4-pisgah-gym-project-back-on-track
photo Repair work at the Pisgah High School Gymnasium should resume in the next few days after state officials issued a stop work order in June because the project was not approved by the Alabama Building Commission.

PISGAH, Ala. — Cooley Gymnasium at Pisgah High School is still partially unusable in the wake of April 2011 tornado damage and efforts to repair it have been called illegal under Alabama building laws.

But that could begin to change in the next few days, according to Jackson County school officials.

Superintendent Ken Harding said Wednesday that work started initially on unapproved plans is now back on track.

“The architect’s been there and the scope of work has been bid out,” Harding said. “Contracts are just waiting to be signed and work should start anytime.”

Jackson County Board of Education attorney John Porter said construction plans under the new contract awarded last week are now approved by the Alabama Building Commission so work on the remainder of the project can resume.