Chattanooga Metropolitan Airport may soon become the nation’s first to be 100 percent energy self sufficient via solar power.
Airport officials Monday agreed to move ahead with initial work on a third phase of its existing solar farm.
The newest phase, slated to come online late this year, would help create enough electricity, which the airport sells to the Tennessee Valley Authority, to pay Lovell Field’s power bill, said Terry Hart, the airport’s chief executive.
Going greener
The airport’s first phase of its solar farm, a 1 megawatt array, consisted of 3,948 solar panels. The second phase, at 1.1 megawatt, added 3,542 panels. The third phase is expected to make the airport energy self-sufficient, officials said.
“It will be great to see that,” Hart said at an Airport Authority meeting, noting that cutting energy costs helps the airport keep down landing and other fees.