The buyer of one of America’s last unfinished nuclear power plants is suing the Tennessee Valley Authority, claiming the federal utility illegally blocked the sale of the plant on Friday.
Attorneys for developer Franklin L. Haney, who is trying to buy the Bellefonte nuclear power plant in Hollywood, Alabama, charged TVA Friday with breach of contract for not completing a previously agreed to sale to Haney’s Nuclear Development LLC for the Bellefonte assets. Haney submitted the winning $111 million purchase offer in a 2016 auction and was scheduled to close the sale Friday.
TVA said the sale could not be completed because Haney had not gained approval from the U.S. Nuclear Regulatory Commission to transfer the construction permits for Bellefonte from TVA.
“The Atomic Energy Act requires that the ownership of a nuclear facility be under the licensing of the Nuclear Regulatory Commission and that (license transfer) is required for us to complete the purchase agreement,” TVA spokesman Jim Hopson said Friday in explaining why TVA scrapped the sale of its Bellefonte plant to Haney.
But in a 14-page federal lawsuit filed in U.S. District Court in Huntsville, Haney’s attorneys argued that TVA’s application of the Atomic Energy Act to the Bellefonte sale “is erroneous.