Judge denies expedited hearing on sale of Bellefonte plant

Bellefonte Nuclear Plant is pictured Monday, July 30, 2018 in Hollywood, Alabama. Nuclear Development LLC successfully bid $111 million for the Bellefonte site, with its two partially-built pressurized water reactors plus infrastructure, including switchyards, office buildings, warehouses, cooling towers, water pumping stations and railroad spurs.
Bellefonte Nuclear Plant is pictured Monday, July 30, 2018 in Hollywood, Alabama. Nuclear Development LLC successfully bid $111 million for the Bellefonte site, with its two partially-built pressurized water reactors plus infrastructure, including switchyards, office buildings, warehouses, cooling towers, water pumping stations and railroad spurs.
photo Franklin Haney, of the Franklin Haney Company, speaks with Tom Decosimo before the event. The Electric Power Board of Chattanooga unveiled its new 100 kilowatt, 4-hour, vanadium redox flow battery made by UniEnergy Technologies of Mukilteo, Washington on September 22, 2017.

A federal judge has turned down a request for an expedited hearing on a challenge to a decision by the Tennessee Valley Authority not to sell its unfinished Bellefonte nuclear power plant to Chattanooga developer Franklin L. Haney, granting TVA more time to respond to Haney’s claim that TVA improperly canceled the sale.

The court decision marks the latest in a long list of delays in determining the future of one of America’s biggest unfinished construction projects which began nearly a half century ago.

U.S. District Court Judge Liles C. Burke ruled last week against holding any expedited hearing on a lawsuit filed in November by Haney’s Nuclear Development LLC, which wants to buy the twin-reactor plant in Hollywood, Alabama. Haney was the top bidder two years ago at an auction for the 1,300-acre plant site with a $111 million purchase offer, which Haney said he was prepared to close in November.

But after granting Haney a couple more weeks to finalize some details, TVA informed Haney a few days before the scheduled Nov. 30 closing on the plant sale that TVA could not sell Bellefonte as a nuclear plant unless federal regulators approved the transfer of the deferred construction permit first granted to TVA nearly 45 years ago to start work on the plant.

Nuclear Development LLC filed its application for the transfer with the U.S. Nuclear Regulatory Commission in November, but the NRC staff is still reviewing the application to ensure that the new owners can adequately comply with the regulatory requirements for building and maintaining a nuclear plant.