TVA hit with $145,000 penalty for inaccurate reports about Watts Bar nuclear plant

Both cooling towers are in operation at Watts Bar Nuclear Plant on Wednesday, Oct. 19, 2016.
Both cooling towers are in operation at Watts Bar Nuclear Plant on Wednesday, Oct. 19, 2016.

Federal regulators today slapped the Tennessee Valley Authority with a $145,000 fine for submitting inaccurate information about the reliability of power service to the last new nuclear reactor licensed in America.

The U.S. Nuclear Regulatory Commission said an inspection this summer at the Watts Bar Nuclear Power Plant near Spring City, Tennessee concluded that TVA repeatedly submitted incomplete and inaccurate information to regulators about the adequacy of an off-site electric power system.

NRC announced the penalty today against TVA after the utility officials admitted they inaccurately reported for at least five years from 2010 to 2015 that two common service station transformers could be counted on as qualified sources of off-site power to be used for accident mitigation. An NRC inspection team identified that the transformers lacked enough capacity to provide power to safety-related equipment at Watts Bar in certain accident scenarios.

The NRC judged TVA’s failure to be at the lowest level for violations that result in penalties.

TVA spokesman Jim Hopson said the federal utility has since taken corrective actions to resolve the problem and he said the violation did not affect public safety or operations since the off-site power was never required.