Long-delayed Grace Baptist rebuild to resume in ‘very near future,’ pastor says

Staff photo by Matt Hamilton / The construction site of Grace Baptist Academy is seen Feb. 26, 2025. Construction to rebuild the school destroyed in a 2020 tornado has been slow going. Church leaders blame a federal funding pause in 2021.
Staff photo by Matt Hamilton / The construction site of Grace Baptist Academy is seen Feb. 26, 2025. Construction to rebuild the school destroyed in a 2020 tornado has been slow going. Church leaders blame a federal funding pause in 2021.


The reconstruction of Grace Baptist Church and Academy’s East Brainerd campus will resume in the “very near future,” the senior pastor said, projecting hope that, nearly five years after a tornado ravaged the church campus, a new chapter in the large drawn-out rebuild project could be soon at hand.

The church and school qualified for federal disaster relief after an EF3 tornado struck the property in April 2020. A groundbreaking for the rebuild took place later that year.

Foundations went in. Steel framing went up. Then, in 2021, construction was halted — a result, church leaders said, of delays in tens of millions of dollars in expected funds from the Federal Emergency Management Agency at a time when the remaining insurance money was running low.

The troubles did not end there. On its website, the church said it had submitted an initial claim for over $70 million to FEMA, but in summer 2022, the agency indicated it wouldn’t pay that much. Instead, it assigned a roughly $30 million grant, church leaders said. After an appeal, the federal agency agreed to reevaluate the figure, indicating it would return with a higher one.