The need to keep traffic flowing on both Interstate 75 and the CSX railway underneath it put the two modes of transportation on a collision course, causing a delay on the $161 million I-75/Interstate 24 interchange project at the Tennessee-Georgia line.
“The contractor experienced delays in gaining access to work on the railroad’s right-of-way for construction of the new bridge on I-75,” Tennessee Department of Transportation spokesperson Rae Anne Bradley said in an email. “These two different modes of transportation – the interstate and the railroad – are both incredibly important. Keeping trains on the track and cars on the road while executing a major road construction project requires extensive coordination and comes with its own set of unique and complex challenges.”
(READ MORE: McCallie tunnels alternating closures for electrical updates)
Agency officials said the project is still on budget, but there was no word on when the I-75 half of the project would be complete. Charleston, Tennessee-based Wright Brothers Construction Co. is the project contractor.
On Friday, the agency said the I-24 half of the project was on track for its original late-2025 completion date.