Tennessee Department of Transportation officials picked a road-building group to take on the state’s first toll project despite a series of bumps the consortium’s companies hit over the past decade-plus, ranging from bankruptcies to price-gouging accusations.
DriveTN’s winning bid included a $9.2 billion construction plan to build toll lanes in Nashville’s southeast interstate corridor, mainly along I-24 to Murfreesboro, with the promise to pay the state nearly $25 billion over the life of a 50-year contract.
No other bidder came close to DriveTN, which, along with its large long-term payout, offered $1.5 billion up front.
Two other bidders offered about $7 billion in payment “concessions” to the state, and a fourth asked for a state subsidy to complete the project.
Transportation Commissioner Will Reid said the companies that make up DriveTN had to meet basic requirements to move on to a second phase of pre-qualifications entailing everything from financial information to the ability to deliver such a large project. In the process, the state turned up no major problems, he said.