The $83 million reconstruction project at Hamilton Place Boulevard and Interstate 75 is 83% complete and on track to open to traffic by summer 2027, officials say.

“The Hamilton Place Boulevard portion of the project is progressing well,” state transportation spokesperson Rae Anne Bradley said by email. “The city’s portion remains on schedule.”

Roads in the mall area should be close to completion by Christmas, according to Bradley, and shoppers shouldn’t feel too much of a traffic pinch around Hamilton Place-area retailers.

“Hamilton Place Boulevard is expected to be near its final alignment before the holiday shopping season,” Bradley said. “Contract restrictions significantly limit construction activities that could affect traffic during this period, and minimal impacts to holiday traffic are anticipated.”

Tennessee Department of Transportation / Plans show how work at I-75 and Hamilton Place Boulevard will reshape traffic.