ATLANTA (AP) — Commercial operation of a new reactor at a Georgia nuclear power plant has been delayed for at least another month.
Georgia Power Co. said Friday that Unit 3 at Plant Vogtle, southeast of Augusta, has a problem in the hydrogen system that is used to cool its main electrical generator. The company now estimates the reactor will begin reliably sending electricity to the grid in July, missing the most recent deadline of June.
The generator is not part of the reactor itself. It’s located in a separate building, where steam from the heat created by fission in the nuclear reactor is piped to spin a turbine, generating up to 1,100 megawatts of electricity.
The unit of Atlanta-based Southern Co. said the problem was a degraded seal. The reactor has been shut down while repairs are made.
The reactor has already hit full power output as part of its testing, which Georgia Power said Friday was 95% complete. But the utility said commercial operation could be put off again if other problems develop.